ProCore Edge 30 North America
IOMM
Use the appropriate minimum wire size (gauge) or larger for the
maximum kilowatt rating of the charger. See section 3 for the
minimum fitted AC input wire size (AWG) per NEC.
The AC service entrance provides two-hole sizes.
4.6.2.1. Use the provided round panel to use the smaller hole size,
or remove this panel to use the larger hole size.
4.6.2.2. Place an appropriate cable gland or conduit clamp in this
AC service entrance hole to secure the cable or conduit.
4.6.3. Connect the three-phase AC input power cables.
Ensure that ground and power cables have been properly stripped (of
approximately 0.5 in. [12.7 mm] of insulation from the ends). Loosen
the AC input terminal screws with a flathead screwdriver and insert
the stripped ends of the power cables. Then insert the stripped end of
the ground wire to the mechanical lug (Figures 16-17).
4.6.4. Re-tighten the screws with the appropriate torque value for
the AC input and ground wire sizes as shown on the torque label.
AC line input positions are interchangeable because the three-
phase input is not phase specific.
4.6.5. Ensure that the cable gland or conduit clamp has been
properly tightened.
5912995 A01
Webasto Charging Systems, Inc.
24 of 68