Commissioning
6.3
Commissioning the VS with bus coupler
Before commissioning the system, the following steps must
have been carried out and completed:
O
You have assembled the valve terminal and the bus coupler.
O
You have connected the bus coupler (see "Electrical
connection" on page 51).
O
You have made the settings and configured the system
(see "Making presettings" on page 54).
O
You have configured the bus master so that it actuates the
valves correctly.
Commissioning and operation may only be carried out by
qualified electrical or pneumatic personnel or an instructed
person under the direction and supervision of qualified
personnel (see "Personnel qualifications" on page 45).
Risk of uncontrolled actuator movements when the
pneumatics are switched on!
There is a danger of personal injury if the system is in an
undefined state.
O
Put the system in a defined state before switching it on.
O
Make sure that no personnel are within the hazardous
zone when the compressed air supply is switched on.
O
Also observe the applicable instructions and safety
information in the VS operating instructions.
1. Switch on the operating voltage.
2. Check the LED displays on all modules.
3. Switch on the compressed air supply.
CAUTION