Assembling The Unit; Warranty Card - Rotex GW-30 C22 Instrucciones De Instalación

Ocultar thumbs Ver también para GW-30 C22:
Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 270
4.3.3

Assembling the unit

1.
Unpack the unit.
2.
Check the content of the packaging, which consists of:
• Unit (A)
• Suspension strip (B)
• Siphon (C)
• Flexible tube (D)
• Installation instructions
• Operating instructions

• Warranty card

3.
Check the unit for any damage: immediately report damages to the supplier.
4.
Install the suspension strip.
5.
Check whether the compression rings are positioned straight in the couplings of
the assembly bracket.
6.
Position the unit: slide it from top to bottom over the suspension strip (B). Make
sure the pipes slide into the compression fittings simultaneously.
7.
Tighten the compression fittings onto the assembly bracket.
The nipples and pipes must not rotate with it!
8.
Open the display valve and loosen the two screws on the left and right of the
display, and remove the front panel.
9.
Assemble the flexible tube (D) onto the outlet of the siphon.
10. Fill the siphon with water, and slide it as far as possible on top of the condense
output connector (E) under the unit.
11. Seal flexible tube (D) of the siphon, if possible together with the overflow pipe of
the inlet combination and the overflow valve, to the sewage via open connection
(F).
12. Assemble the air supply and the burning gas outlet (see par. 5.6).
13. Assemble the cover and tighten the two screws to the left and the right of the
display, and close the display cover.
4.3.4
Apply cover plate (optional)
Suspend the converted top edge of the cover plate from the washers underneath the
bottom of the unit, and slide the cover plate as far back as possible.
Danger: risk of burning
In case of high leaving water set ponts for space heating (eighter a high fixed set point
or a high weather-dependent set point at low ambient temperatures), the heat
exchanger of the boiler can be very hot, for example 70°C.
Beware that in case of a tapping demand, the water can initially have a higher water
temperature than requested.
In this case, it is recommended to install a thermostatic valve to prevent scalding.
This can be done according to the schematics below.
a=boiler, b=DHW from boiler, c= cold water inlet,
d=shower, e=thermostatic valve (field supply)
15

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

Gw-30 c28Gw-30 c33Rkombg22aav1Rkombg28aav1Rkombg33aav1

Tabla de contenido