5. Cabinet Installation
4
Use a 13 mm open-end wrench to remove the shipping brackets at the front
and rear of the Distribution Center. Be extremely careful, as the Distribution
Center could shift unexpectedly after bracket removal. Save the brackets and
bracket hardware for later use. Position at least one person at the front of the
Distribution Center and one person at the rear of the Distribution Center. Slowly
push the Distribution Center toward the back of the shipping pallet until all
four casters go over the edge of the pallet and touch the floor. WARNING: Use
at least one assistant when removing the Distribution Center from the
pallet. Be extremely careful when moving the Distribution Center.

5.3 Placement

1
Use the casters to move the Distribution Center for a short distance over a
level, smooth, stable surface by pushing it from the front or rear (not the side
panels). Do not attempt to roll the Distribution Center over long distances. The
Distribution Center should be moved close to its installation location inside its
shipping container before it is unpacked. (Use a forklift or pallet jack to move
the shipping container.) WARNING: Do not push or pull the Distribution
Center at the side panels or pull the enclosure toward you.
If required, the Distribution Center can be lifted by attaching 4 user-supplied
M8 diameter eye bolts to the threaded holes near the upper corners of the
Distribution Center frame. Use steel bolts with an ISO strength rating of 8.8 or
higher. WARNING: Only experienced equipment operators should attempt
to lift the Distribution Center. Use appropriate equipment and follow all
applicable safety procedures and regulations.

5.4 Leveling

WARNING!
Level the Distribution Center before attempting to install wiring. The casters are not designed to
provide long-term support for the Distribution Center. Use the levelers to provide long-term support.
1
After the Distribution Center has been moved to the installation location, use
a carpenter's level to check the slope of the floor. If the floor slopes more than
1%, choose an alternate installation site.
2
Use an 18 mm open-end wrench to lower each leveler
floor. (There are 4 levelers, 2 at the front and 2 at the rear.) Make sure each
leveler contacts the floor solidly.
Note: Lower a leveler by turning it clockwise; raise a leveler by turning it counter-
clockwise.
until it reaches the
A
7
4
1
FLOOR
1
2
A