General Setup Via Hart - Mettler Toledo M400/2H Guía De Configuración Rápida

Ocultar thumbs Ver también para M400/2H:
Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 51
7

General Setup via HART

Besides the on-site operation you can configure the M400 transmitter either via a configuration
tool, an asset-management-tool or via a HART handheld terminal.
Prerequisite: The M400 transmitter and the sensor are mounted and electrically connected.
Configuration tool or asset-management tool
h
Note: The configuration tool PACTware™ is on the supplied CD-ROM. The DTM you can down-
load via Internet "www.mt.com/m400-downloads".
For steps 1 to 5 and step 13 refer to the documentation of the tool.
1. Install configuration tool e.g. PACTware or asset-management-tool.
2. Install DTM for HART interface and DTM for M400 transmitter.
3. Update device catalog.
4. Build up connection. Check COM port settings if necessary.
5. Select Sensor Type.
Menu path: Detailed Setup > Measurements > Channel Setup > Sensor Setup.
6. Load configuration from device.
7. Set Tag or/and Long Tag.
Menu path: Device Setup > Detailed Setup > HART Info
8. Set Date and Time. Set the time in the 24 hour format. The time format cannot be
changed. Menu path: Device Setup > Set Date/Time
9. Set range of the analog output signal.
Menu path: Detailed setup > Output Condition > Analog output > Range
• URV (Upper Range Value) and LRV (Lower Range Value): The values can be changed
to the current measurement range. The values have to be within the measurement limits
of the sensor.
• USL (Upper Sensor Limit) and LSL (Lower Sensor Limit): The limits are defined by the
sensor and cannot be changed.
10. Define the process variables PV, SV, TV and QV
Menu path: Device Setup > Detailed Setup > Measurements > Channel Setup
en
46

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

M400g/2xhM400/2xh

Tabla de contenido