2.0 - TECHNICAL DATA

• Use
• Ambient temperature (TS)
• Maximum operating pressure
• Modulating ratio
• Adjusting angle
• Spherical
• Flanged connections to be coupled with PN 16 flanges : (DN 50 - DN 65 - DN 80 - DN 100 - DN 125 - DN 150 - DN 200)
• ANSI 150 flanged connections
Note: For the actuator technical data, refer to paragraphs 5-6-7 and pages 39-40-41.

3.0 - COMMISSIONING THE DEVICE

3.1 - OPERATIONS PRIOR TO INSTALLATION

• It is necessary to close the fluid/gas upstream of the valve prior to installation;
• Make sure that the line pressure DOES NOT EXCEED the maximum pressure declared on the product label;
• Any protective caps (if any) must be removed prior to installation;
• Valve pipes and insides must be clear of any foreign bodies;
• Make sure the inlet and outlet counter-flanges are perfectly coaxial and parallel in order to prevent unnecessary mechanical
stress to the body. Also calculate the space to insert the seal gasket;
• With regard to tightening operations, equip yourself with one or two calibrated torque wrenches or other controlled locking
tools;
• With outdoor installation, it is advisable to provide a protective roof to prevent rain from damaging the electrical parts of
the device;
• Prior to carrying out any electrical wiring operations, make sure that the mains voltage matches the supply voltage indicated
on the product label;
• Cut out power prior to proceeding with wiring;
• According to the plant geometry, check the risk of explosive mixture arising inside the piping;
• If the solenoid valve is installed near other devices or as part of an assembly, compatibility between the solenoid
valve and this other device must be evaluated beforehand;
• Provide a protection against impacts or accidental contacts if the solenoid valve is accessible to unqualified
personnel.
3.2 - INSTALLATION (see examples in 3.4)
• Assemble the device by flanging it, with the due seals, onto the plant with pipes whose flanges are consistent with the
connection being attached. The gaskets must be free from defects and must be centred between the flanges;
• If, after installing the gaskets, there is still an excessive space in between, do not try to reduce the said gap by excessively
tightening the bolts of the device;
• The arrow, shown on the body of the device, needs to be pointing towards the application;
• Insert the relative washers inside the bolts in order to prevent damage to the flanges during tightening;
• When tightening, be careful not to "pinch" or damage the gasket;
• Tighten the nuts or bolts gradually, in a "cross" order (see the example below);
Madas Technical Manual - 9|9.2 - REV. 0 of 12
: gas hot air, natural gas, town gas, LPG and other non aggressive fuels
: -40 ÷ +70 °C
: 500 mbar
: 1:10
: Max 90°
: 30°
ISO 7005 / EN 1092-1
: on request