EAA
GB
– Cable set (mains power and control cable,
4 m long)
– Compressed air line (4 m long)
– Aluminium pipe (50 mm in diameter,
350 mm long) for suspending the EAA
– 2 x retaining plates, incl. screws and dow-
els
– Pipe/Suction hose adapter
– Mounting plate for maintenance unit
– Drain hose for condensate
Procedure
Remove the maintenance unit [2] from
the rear panel of the EAA (not EW ver-
sion).
Remove the rear panel of the EAA.
Secure the mounting plate [6-4] to the
top section of the EAA using the four
screws [6-3].
Attach the maintenance unit [6-1] to the
mounting plate [6-4] using the screws
[6-6].
Attach the enclosed air hose [7-1] with
screw clamp [7-2] to the elbow piece
with hose connector [7-3] on the mainte-
nance unit.
Cut the blue fitted air hose (D16 mm)
[8b-3] to a total length of 400 mm.
Turn the elbow piece [6-5] downwards
and insert the shortened blue air hose.
Attach the condensate drain hose [5-11]
to the connection point [6-2] on the
maintenance unit.
Lay the hoses inside the EAA as shown in
Fig. [5].
Insert the other end of the blue hose into
the connector [5-1].
Grease the bottom section of the alumin-
ium pipe and slide into the Y-piece on the
EAA [5-8] up to the stop.
Tighten the two screws [5-9] on the grip-
per clamp to a tightening torque of 6 Nm.
The EAA is now seated securely on the
aluminium pipe.
Connect all the hoses in the EAA (see chapter
8 "Connections in the EAA") before following
the wall mounting instructions described be-
low.
Secure the rear panel to the EAA using the
screws supplied.
20
Attach the lower retaining rail to the wall
first (see Fig. [8a]). If the wall is made of
concrete, use the enclosed dowels. Note:
leave 1 m of clearance between the panel
and the ceiling.
Insert the EAA into the lower retaining rail
from above. The hooks must engage in
the EAA housing.
Attach the upper retaining rail [8b-1] to
the EAA. The hooks must engage in the
EAA housing.
Attach the upper retaining rail to the wall
(see Fig. [8b]). If the wall is made of con-
crete, use the enclosed dowels.
Attach the adapter [8b-2] to connect the
suction hose to the aluminium pipe. Alter-
natively, you can extend the aluminium
pipe by attaching a plastic pipe (install
with antistatic discharge) or steel pipe for
extraction systems, and then attach the
adapter afterwards.
This version does not allow the attach-
ment of hose holders (see chapter 8.4).
7.3
Ceiling installation
The assembly set contains:
– Cable set (mains power and control cable,
2.5 m long)
– Compressed air line (2.5 m long)
– Aluminium pipe for suspending the EAA
– Hydraulic pipe
– 2 x clamps with rivet
– 2 x cable clips
– Bracket
Procedure
The aluminium pipe is 1.6 m in length on
delivery. The pipe can be shortened at the
open end if necessary. We recommend
adapting the length of the pipe so that the
tool holder [1-1] on the EAA is positioned
at forehead height. Always deburr the
aluminium
pipe
length!
Remove the rear panel of the EAA.
Grease the bottom section of the alumin-
ium pipe and slide into the Y-piece on the
EAA [5-8] up to the stop.
Tighten the two screws [5-9] on the grip-
per clamp to a tightening torque of 6 Nm.
The EAA is now seated securely on the
aluminium pipe.
after
cutting
to