Checks Before Startup; Preliminary Checks - Galletti ACQVARIA 10 Manual De Instalación, Uso Y Mantenimiento

Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

Front panel/grille assembly
The front panel/grille, available in RAL9003 and RAL9010 ver-
sions, is delivered in a separate cardboard box:
Ū AQYGR30 for models AQ 10-20-30
Ū AQYGR60 for models AQ 40-50-60
Before installing the front panel: (Fig.11 )
Ū Remove the screws (1) securing the retainers (2) on each side
(remember to put these screws back in place after installa-
tion).
Ū To open the grille (3), move the two retainers (2) in the direc-
tion of the arrow.
Ū Open the grille (3) by 45°.
Ū Detach the control panel's safety cable (4) (remember to at-
tach it again after installation).
Ū Lift the grille to remove it from the control panel.
» Fig�11
To install the front panel: (Fig.12 )
Ū Turn the two locking clips (5) downwards.
Ū Attach the control panel of the panel (6) to the unit by means
6

CHECKS BEFORE STARTUP

6.1

PRELIMINARY CHECKS

Make sure:
Ū make sure that the power cable is not damaged, if it is dam-
aged must be replaced by the manufacturer or its technical
assistance service or in any case by a person with a similar
qualification, in order to prevent any risk,
Ū that the unit is stable and perfectly level,
Ū that the electrical cables are well tightened on their terminal
blocks (if they are not tightened properly, the terminals may
cause the terminal block to overheat),
Ū that the electrical cables are properly insulated from any
sheet metal or metal parts that could damage them,
Ū that the unit is well earthed,
Ū that no tools or any other foreign objects have been left in
32
ACQVARIA I
of the two hooks (7), matching them to the locking clips (5).
Ū Check the exact position of the panel's control panel in re-
lation to the suspended ceiling. Adjust the position of the
indoor unit as necessary.
Ū Attach the panel's control panel to the unit using the special
screws and washers (8) provided.
Ū Put the grille (3) in place, making sure that the filter (9) is cor-
rectly positioned.
Ū Hook the safety cable to the control panel, close the grille,
and put the screws securing the retainers (2) back in place.
» Fig�12
the unit,
Ū that the filter is properly installed,
Ū that the coil is clean,
Ū that the hydraulic fittings are properly tightened,
Ū that the condensate drain is properly connected and not ob-
structed,
Ū that the condensate drain pan is clean,
Ū that the drainage pipes are securely fastened.

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

Acqvaria 20Acqvaria 30Acqvaria 40Acqvaria 50Acqvaria 60

Tabla de contenido