58 | ACS 763/863 | Initial settings
5.12
Tank filling
This procedure transfers refrigerant from an external
tank to the station internal tank. The operational
capacity of the internal tank is 17.4 kg.
i
Use the arrow buttons to move the cursor; use the
keypad to enter a value.
1. The station displays the fields to enter the desired
amount of refilling, the rechargeable amount of
refrigerant, and the amount of refrigerant which can
be recovered inside the internal tank.
2. Enter the desired amount of tank refilling and select
to proceed.
i
Add at least 4 kg (8,0 lb) of refrigerant to make sure
that the quantity available is enough for the charge.
3. Connect the low pressure service hose (blue) to the
liquid fitting on the external tank.
4. Open the valve of the connection on the hose
turning the ring nut clockwise.
5. Place the external tank in such a way that the
refrigerant flows into the connection.
6. Open the external tank valve.
7. Select
to start filling the tank.
8. If the refrigerant analyzer is installed, the station
verifies that the refrigerant contained in the cylinder
is R1234yf and is not contaminated.
« The display shows
REFRIGERANT ANALYZER
INITIALIZATION
ANALYSIS
"
The station starts filling the internal storage tank. This
takes 15 - 20 minutes.
i
If the station detects a problem with the refrigerant
contained in the cylinder, refer to the Refrigerant
Analyzer section in this manual.
i
The station stops when the specified amount of
refrigerant has been transferred to the internal tank
or when the external tank is empty.
9. Follow the instructions on the display.
10. Close the valve of the connection turning the ring
nut counterclockwise.
11. Close the external tank valve.
12. Select
to return to the Functions Menu.
"
The station is ready for operation.
i
It is necessary to complete the entire Initial Setup
sequence before using the station. If it is not
completed, this initial setup sequence is repeated
every time the station is switched on.
i
It is not necessary to calibrate the scale as it has
been calibrated at the factory.
|
SP00D00490
2019-03-05
and
REFRIGERANT SAMPLE
i
When the tank is filled, the display does not show
the same quantity as the programmed one. The
display shows the amount of refrigerant available for
charging, equal to 2.2 kg less than the total amount
of refrigerant contained in the tank.
5.13
Unit activation
Failure to register and activate the station within
30 days of initial start-up causes the station to lock and
the impossibility to use it.
1. Call up the Main Menu.
2. Select
.
3. Select
.
4. Select Settings.
5. Select Unit Activation.
« The display shows
PERIOD REMAINED to activate the unit.
Activate now?
6. Select
to start the activation process.
« The display shows
code: xxxxxxxxxxx
Enter the code: xxxxxxxxxxxxxxxxxxxx
7. Open an Internet browser on a personal computer
and enter https://register.servicesolutionsportal.
com.
8. Enter your username and password, and log in to
access the website.
i
If you are accessing the site for the first time,
click the Registration button to create your own
username and password.
9. Enter the Personal Identification Number of the
station to receive an activation code.
10. Enter the activation code in the correct field on the
station.
i
Enter the code exactly as it was received. Use
uppercase if necessary.
11. Note the activation code and keep it in a safe place.
12. Select
to confirm.
« The station displays a message indicating that
the activation has been successful.
13. Select
to print or
"
Activation of the station has been successful.
XX DAYS OF THE TRIAL
to exit the function.
Robert Bosch GmbH

Publicidad

loading

Este manual también es adecuado para:

Acs 863Acs 863-oe