4 INSTALLATION
4.2 Wiring (Continued)
3. Maintain spacing of at least ½ in. between conduit hubs/fittings and uninsulated live
conductors. Use cable ties to secure conductors to each other and to maintain spacing.
4. Plug in the RJ12 cables to the VERIFEYE 61N00 and feed the cable out of a conduit hole.
NOTE: Connect the communication protocol being used at this point. For more detailed
instructions on how to set up the communication protocols please refer to the VERIFEYE
61P00 instruction manual.
5. Connect the current transformers to the load and connect them into the appropriate
L1/L2/L3 input on the meter using an RJ12 cable.
6. Put fuses provided in the black bag into the fuse holders.
7. Close the metal plate and screw it back down. The VERIFEYE 61N00 should now be
powered and functioning.
RJ12 Cable Locations on VERIFEYE 61N00
6
CCSRJ Sensor Cables
3x I CTSxx/CRSxx Sensors