Initial Setup and Start
3
3
Illustration 3.9 LCS Tool - List of all Inverters Connected to the Inverter Manager
10.
If sufficient PV power is present and the grid
code conditions are met, the inverters connect to
the grid.
11.
Upon commissioning, it is possible to download a
commissioning report under the menu 'Reports'.
Illustration 3.10 LCS Tool - Commissioning Report
26
The report contains all information about inverter
settings, including actual disconnect values for
each inverter. See Illustration 3.10.
L00410644-01_2q / Rev. date: 2014-06-02