4 - MACHINE INSTALLATION

4.1 Warnings

Installation must be carried out by qualified person-
nel, according to the instructions supplied by the
manufacturer and in compliance with current laws.
The machine must be positioned and installed in a
place where use and maintenance are performed
exclusively by qualified personnel.
The machine can be used in places set up for staff
kitchen areas in shops, offices and other working
environments; holiday farm houses; by clients in
hotels, motels and other types of accommodation;
bed and breakfast settings; etc.
4.2 Preparation of system for
installation
Prepare the machine's support on a flat horizontal,
even, dry, smooth, sturdy, stable surface positioned
at such a height that the cup warming surface is
more than 150 cm from the ground.
Do not use water jets, or install in places where
water jets are used.
To guarantee regular operation, the device must
be installed in places where the temperature is
between +5°C and +32°C and the humidity does
not exceed 70%.
If the machine is exposed to temperatures below
+ 0 °C, proceed as follows:
- ensure that the machine has passed 24 hours
in a place where temperature is higher than +
15 °C before turning it on.
The machine is powered by electricity and it needs
the following to operate:

- connection to mains electricity.

- connection to mains water.

- connection to drainage circuit.

4.2.1 Connection to mains electricity
Warnings:
- The connection to mains electricity must be
done by qualified personnel.
- The wiring must be done in compliance with
current laws and earthed.
The machine is supplied with a power cord without
a plug; for a permanent electrical connection
between the appliance and the mains electricity, fit
a safety omnipolar switch with a minimum opening
between the contacts of overvoltage category III,
suitably sized for the load and in compliance with
the current regulations in force.
Use the special steel tie provided to secure the
power cable, filling and drainage pipes (Fig. 10).
4.2.2 Connection to mains water
Make sure that the water supply line is connected
to a drinking water network with operating pressure
between 0 and 6 bar (0 - 0.6 MPa).
If the water network has pressures above 6 bar
(0,6 MPa), install a pressure reducer. Provide a
water shut-off valve upstream of the machine's
connection.
The water inlet pipe (Fig. 03; pos. 14) has a G
3/8" thread.
Use the special steel tie provided to secure the
power cable, filling and drainage pipes (Fig. 10).
4.2.3 Connection to drainage circuit
Connect the drip tray drainage pipe (Fig. 03; pos.
13) to the G 3/4" connector and to a pre-installed
open or serviceable drainage siphon.
The machine is pre-configured with boiler drainage
pipe and solenoid valve (Fig. 03; pos. 15). Connect
it to the drain, keeping in mind that the discharge
water can reach a temperature of 130°C (266°F).
Use the special steel tie provided to secure the
power cable, filling and drainage pipes (Fig. 10).

4.3 Instructions for water softener

Prepare the machine connection as indicated in
Figure 4.
For use and maintenance, refer to the instructions
for the water softener
A – Connect to the water inlet pipe
B – Connect to the mains drinking water