EN
m
CAUTION
The height of the boiler is to be such that disassembly
and maintenance interventions are facilitated.
2.9
Plumbing connections
The plumbing connections have the following characteristics
and dimensions.
48
Sc
=
65 65 65 65
M
U
G
E
R
400
Description
M - System delivery
R - System return
U - Domestic hot water output
E - Domestic hot water inlet
G - Gas supply
Sc - Condensate outlet
2.9.1
Plumbing accessories (optional)
To facilitate plumbing and gas connections to the systems, the
accessories as shown in the table below are available and are to
be ordered separately from the boiler.
DESCRIPTION
Installation plate
Curve kit
Curve and valve kit with connections from DIN
to SIME
Cocks kit
Valve kit with connections from DIN to SIME
Wall mount replacement kit for other makers
Fitting protection Kit
Polyphosphate dosing kit
Dosing recharge kit
kit instructions are supplied with the accessory itself or
NOTE:
are to be found on the packaging.
Sc
95
=
175
Fig. 13
Brava One HE ErP
25
30
35
Ø 3/4" G
Ø 3/4" G
Ø 1/2" G
Ø 1/2" G
Ø 3/4" G
Ø 20 mm
CODE
8075441
8075418
8075443
8091806
8075442
8093900
8094530
8101700
8101710
2.10
Condensate outlet/collection
In order to collect the condensate, it is recommended that:
– the appliance condensate outlets and the smoke outlet are
ducted
– a neutralising device is prearranged
– the outlet incline is >3% .
m
CAUTION
– The condensate outlet duct must be airtight,
suitably sized to that of the siphon and must not be
restricted at any point.
– The condensate outlet must be constructed in full
compliance of the National or Local regulations in
force.
– Before commissioning the appliance, fill the siphon
with water.
2.11
Gas supply
Brava One HE ErP
boilers leave the factory prearranged for gas
G20 and can also work with G230-G31 without the need for any
type of mechanical conversion. Simply select parameter "03"
(see "Parameter setting and display") and set the type of gas
to be used.
If changing the type of gas to be used, carry out the entire
appliance "COMMISSIONING" phase.
Boiler connection to the gas mains must be carried out in full
compliance with installation Standards in force.
Before connecting the boiler to the gas mains, the user must
ensure that:
– the type of gas is correct for the appliance
– the pipes are clean
– the gas supply pipe is the same dimension as or greater than
that of the boiler fitting (G3/4") and with a load loss less than
or equal to that contemplated between the gas mains and the
boiler.
a
WARNING
Once installation has been completed, check that
the joints are air tight as indicated in the installation
Standards.
40
m
CAUTION
It is recommended that the gas line has a suitable
filter.
m
CAUTION
If the gas supply is changed from G20 to G230 or G31,
mark the box on the TECHNICAL DATA PLATE.
G230 - 20 mbar
Or:
G31 - 37 mbar
X
X
75