8. Operation, shutdown and disposal

8. Operation, shutdown and disposal

8.1 General information

After correct electrical connection and fill-
ing with lubricant the pump is ready for
operation.
Start-up respectively shutdown is effected
by switching the superior machine or vehicle
on or off.
NOTICE
Damage to the pump
Make sure that no dirt enters the reservoir
during the filling procedure.
Overfilling of the reservoir
Consider lubricant expansion by increased
temperature.

8.2 Filling the reservoir during operation

Filling via iller itting
• Connect the filling adapter to the filler
fitting (5) and fill reservoir with lubricant
until shortly below MAX marking. To
do so, observe the notes contained in
chapter 4.8.

8.3 Temporary shutdown

Temporarily shut the system down by dis-
connecting it from the power supply.

8.4 Shutdown and disposal

In case of final shutdown follow the appli-
cable rules and regulations on disposal. The
product can also be returned to the manu-
facturer for proper disposal, in which case
the customer is responsible for reimbursing
the costs incurred. The parts are recyclable.
Disposal Fig. 12