D3330
5.8
Combustion head setting
6080
Installation
Fig. 10
Fig. 12
D462
Notches no.
Light oil delivery in 2nd stage kg/h
12
D1249
The setting of the combustion head depends exclusively on the
burner delivery in the 2nd stage - in other words, the combined
delivery of the two nozzles selected in table (Tab. A).
Turn screw 4)(Fig. 12) until the notch shown in diagram (Fig. 13)
is level with the front surface of flange 5)(Fig. 10, page 12).
Example:
The RL 190 Model with two 18 GPH nozzles and 12 bar pump
pressure.
Find the delivery of the two 18 GPH nozzles in (page 7, Tab. A):
76.4 + 76.4 = 152,8 kg/h.
Diagram Fig. 13 indicates that for a delivery of 152,8 kg/h the RL
190 Model requires the combustion head to be set to approx.
three notches, as shown in Fig. 12
D1250
GB
Fig. 11
Fig. 13