3. Slide the pipe seal washer onto the end of the
compression fitting.
4. Insert the completed assembly into the hole in the
pipe and tighten the clamp.
5. Test for leaks.
6. If the pipe is larger than 2" in diameter, two (2)
clamps joined together will be required per each
hole.
Clamp
Jam Nut
Seal
Figure 7.
Saddle Clamps
3.3.2
Pipe Tap
1. If using a pipe tap, drill a 7/16" hole and tap a 1/4"
NPT hole. Be careful not to over tap the hole. See
Figure 8.
2. Apply Teflon
tape to the threads on the
®
compression fitting and screw securely into the
pipe.
3. Test for leaks.
4. Cut the tubing to the appropriate length. Slightly
loosen the compression fitting in the pipe and insert
the tubing.
5. Take the free end of the tubing and insert it into the
compression fitting on the flow cell.
Figure 8.
Pipe Tap and Threaded Fitting
C1900 ORP and pH ChemLink™ Controller
Tube
Fitting
Tube
Fitting
|
Installation & Operation Manual

Section 4. Electrical Connections

4.1
Installation of the ORP and pH Sensor
onto the Flow Switch Assembly
1. Unpack the sensors and remove the protective bottle
and o-ring.
2. Set aside the o-rings and save the bottles for
winterizing or reshipping.
3. Remove the compression fitting nut from the flow
cell and slide it up onto the sensor.
4. Slide the o-ring from the bottle onto the sensor.
5. Insert the sensor into the compression fitting on the
flow cell assembly. The sensor tips should extend
below the water line in the flow cell. See Figure 9.
6. Hand-tighten the nut of the fitting, do not use a
wrench.
7. Coil any extra sensor cable externally, not in the
controller box.
Sensor Tip
Figure 9.
Sensor Installation
Controller
ORP
Compression
Fitting