Tripp-Lite SmartOnline SU5KRT3UTF Instrucciones De Instalación página 11

Ocultar thumbs Ver también para SmartOnline SU5KRT3UTF:
Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

AC Connections and UPS Start-Up
Hardwire Input and Output Wiring Instructions
(SU5KRT3UTFMB & SU6KRT3UTFMB only)
Note: The tightening torque is 1 n•m (10 lb•in.).
CAUTION: This type of connection must be performed by qualified professional electrical service personnel only. When making
connections, check that the AC mains power to the UPS is OFF. Connect the ground wires from the cables to the chassis
ground lug. Always connect the ground wires first.
Be sure to observe the Input Line Configuration, Breaker and wire AWG as outlined in the UPS Input and Output Overview
table, detailed in this section.
Note: Select models include an accessory AC cord with L6-30P plug. If your UPS model has an attached cord, the UPS rating will change.
Refer to the product nameplate for more information.
1. Detach the PDM from the UPS.
2. Unscrew the four screws to remove the terminal strip cover and slide out.
3. Connect the two sets of L1, L2 and ground wires (1 Input, 1 Output) according to markings on the connectors. Be sure to
connect one set of wires to the input terminals and the other set to the output terminals.
Note: The included ground lug needs to be added to the ground stud, as shown.
PDM Outlets and Outlet
Configuration will Vary by
Model
L1 In
L2/N In
Hardwire Input
Ground
L1 Out
L2/N Out
Ground
Hardwire Output
11