3.7 INSTALLING THE GEARMOTOR
a
Incorrect installation may cause serious physical
injury to the person working on the system or to its
future users.
Before starting to assemble the automation,
complete the preliminary checks described in the "
Pre-installation checks" and "Product usage limits"
paragraphs.
If there is a support surface:
open the cubicle panel
1.
15
place the cubicle on the anchoring surface and mark the
2.
points corresponding to the slots
16
move the cubicle and drill the surface through the marked
3.
points
insert 4 expansion bolts (not supplied)
4.
arrange the cubicle properly and secure it with the
5.
appropriate nuts and washers (not supplied).
17
If there is no support surface:
dig the hole to insert the foundation plate
1.
The anchoring surface must be completely lat and
Note
smooth. If the surface is made of concrete, the latter
must be at least 0,15 m thick and must be suitably
reinforced with iron cages. The concrete must have a
volume above 0.2 m
to 0.8 m
, that is, equal to a square base with sides each
2
measuring roughly 0.9 m). The plate can be anchored to
the concrete using the 4 expansion bolts, equipped with
12 MA screws capable of withstanding a tensile load of
at least 400 kg. If the anchoring surface is made of a
different material, it is necessary to verify its consistency
and whether the four anchoring points can withstand
a load of at least 1,000 kg. Use the 12 MA screws to
fasten the plate.
arrange the pipes for routing the electrical cables
2.
fasten the four anchor bolts (A) to the foundation plate,
3.
inserting a nut and washer (supplied) on each, on the
upper and lower sides of the plate
m
The lower nut must be screwed up to the end of the
thread.
18
B
(a 0.25 m thickness corresponds
3
A
ENGLISH – 59