17
ASSEMBLY
17.1
Preparatory activities
17.1.1 Checking delivery content
Always note visible transport damage on the delivery note and check the machine immediately
after unpacking for transport damage or missing or damaged parts. Report any damage to the
machine or missing parts immediately to your retailer or freight forwarder.
17.1.2 Cleaning and lubrication
Before you install and commission the machine at the intended location, carefully remove the
anti-corrosion protection and grease residues.
Under no circumstances should you use nitro thinner or other cleaning agents that could attack
the machine's paint.
Oil bare machine parts (e.g. machine bed, tailstock sleeve, feed spindle) with an acid-free
lubricating oil.
17.1.3 Site requirements
Insufficient rigidity of the ground leads to the superposition of vibrations between the
lathe and the ground (natural frequency of components). If the stiffness of the
overall system is insufficient, critical speeds are quickly reached, which leads to poor
turning results.
Select a suitable installation location for the machine.
The place of installation should have:
adequate lighting.
•
a plain, level floor with minimum vibration values (e.g. concrete).
•
The machine itself should be mounted on a solid work surface that is also straight
•
and low-vibration (e.g. solid workbench).
The exact space required and the required load-bearing capacity of the ground result from the
technical data (dimensions, weight) of your machine. When designing the working area around
the lathe, observe the local safety regulations. When dimensioning the required space, take into
account that the operation, maintenance and repair of the machine must be possible without
restrictions at all times.