Commissioning

6 Commissioning
n
Users' qualifications: Technical expert, see
CAUTION!
Incorrect metering due to sensor failure
Possible consequence: Slight or minor injuries, material damage
If a sensor fails then there may be an incorrect reading at the input of the controller/measuring
device
This may result in uncontrolled metering
The operator must therefore ensure that no subsequent damages can result from this
CAUTION!
Do not switch off the measuring system during intermittent operation!
A run-in time will be necessary following operation without chlorine. Switch on metering
equipment with a time delay if necessary!
If no chlorine is added for a long time ( ~ 1 week) then the sensor must be reactivated using
emery. The sensor is once more ready for use after expiration of the run-in time and a repeat

calibration.

Run-in time
The sensor requires a specific run-in time to display a steady display value.
Initial commissioning:
After cleaning the working electrode and counter
electrode:
Repeat operation:
Electrolyte replacement:
* the exact run-in time depends on the application.
22
Ä Chapter 1.2 "Users' qualifications " on page 10
1 - 24 h (typically 6 h)*
1 - 24 h (typically 6 h)*
1 - 24 h (typically 6 h)*
1 - 3 h