Wall Installation - Baxi PRIME 1.24 Manual De Uso Destinado Al Usuario Y Al Instalador

Caldera mural de gas de condensación
Ocultar thumbs Ver también para PRIME 1.24:
Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 98
6.2.1

Wall installation

Cover the boiler to protect it against dust produced during drilling in the wall.
Establish its exact position on the wall (see the wall template in paragraph 3.3) and install it as follows:
• Identify the points at which to drill the fixing holes in the wall and check that they are level, and drill the holes using a Ø 8 mm
tip (1).
• Insert the Ø 8 mm dowels and fix the bracket to the wall using Ø 6 mm screws and washers (2).
• Lift the boiler (two people are required to do this) and position it on the wall at the point of the hooks on the supporting bracket
(3).
• Make sure that the boiler is positioned vertically, and that the maximum deviation does not exceed 15 mm as shown in figure
(4).
6.2.2
Access to the boiler's electrical connection board.
To access the electrical connection board, undo the two screws under the cover of the front panel as shown in the figure.
6.2.3
Access to the internal components of the boiler
To access the components of the boiler remove the front panel by undoing the two clips C1-C2 under the boiler as illustrated in
the figure.
19
0 ÷ 15 mm
0 ÷ 15 mm
BO_0000051
BO-0000014
7696306 (01-12/17)