Three-phase operation
u Connect the conductors of the supply line to the
terminals L1, L2, L3 N and PE as per the terminal
labelling.
u Comply with the connection data for the termin-
als.
1 "4 Technical data" [} 10]
5.6.3 Shunt release
Requirement(s):
ü The shunt release is installed in the upstream
electrical installation.
1 "5.2.2 Protective devices" [} 13]
Fig. 9: Shunt release connection
XG3
3
1
Fig. 10: Schematic circuit diagram: Connecting an
external shunt release
u Strip the cable.
u Strip the conductors 10 mm.
1
3
Shunt release
AC/DC
u Connect the conductors to the plug connector
(included in the scope of delivery).
u Insert the plug connector into XG3.
Terminal
Connection
(XG3)
5
Shunt release
6
Power supply
n Max. 230 V AC or max. 24 V DC
n Max. 1 A
u Comply with the connection data for the switch-
ing output.
1 "4 Technical data" [} 10]
u Route the line as shown in the illustration above
and secure it to the marked components using
cable ties (included in the scope of delivery).
In the event of a fault (welded load contact),
the shunt release is activated and the
product is disconnected from the mains.
EN
17