HotSwap MBP-module operation
UPS start-up with the HotSwap MBP module
1 - Check that the UPS is correctly connected to the HotSwap MBP module.
2 - Set switch (53) to the Normal position.
3 - Start the UPS by pressing the ON/OFF button (27) on the UPS control panel.
The load is supplied by the UPS.
LED (51) "UPS ON - OK to switch" on the HotSwap MBP module goes ON.
HotSwap MBP-module test
1 - Set switch (53) to the Bypass position and check that the load is still supplied.
2 - Set switch (53) back to the Normal position.
2.8 UPS connection without a FlexPDU or HotSwap MBP module
Check that the indications on the name plate located on the back of the UPS correspond to the AC-power source
and the true electrical consumption of the total load.
Tower model
8
32
RT model
Note. The UPS charges the battery as soon as it is connected to the AC-power source, even if button (27) is not
pressed.
Once the UPS is connected to the AC-power source, eight hours of charging are required before the battery can
supply the rated backup time.
34008097EN/AE - Page 14
51
52
53
7
9
8
7
9
32
The HotSwap MBP module has a rotary
switch (53) with two positions:
Normal - the load is supplied by the UPS,
Bypass - the load is supplied directly by
the AC-power source.
1 - Connect the UPS socket (9) to the AC-
power source using the power cable from
the equipments to be protected.
2 - Connect the loads to the UPS using the
cables (32).
It is preferable to connect the priority loads
to the 3 outlets marked (8) and the non-
priority loads to the 3 outlets marked (7)
that can be programmed in pairs (1 and 2).
To program the outlets, the EATON
communications software is required.