INSTALLATION OF THE MOTOR
PREPARATORY STEPS
CAREFULLY OBSERVE EUROPEAN REGULATIONS EN12445 AND
EN12453 (WHICH REPLACE UNI 8612).
Always check the following:
• Your gate should have a strong and suitable build; no
wickets should be present on the sliding gate.
• The sliding gate should not tilt excessively during its entire
run.
• The gate should be able to slide freely on its guiding
surface without an excessive friction.
• Install both closing and opening limit switches, in order to
prevent the gate going off the guiding surface.
• Remove any manual locks.
• Bring power cable ducts near the bottom of the gate
(diameter 20 / 30 mm) and of the external devices
(photocells, flasher, key selector).
POSITIONING OF THE MOTOR
To fix HYPERFOR, follow the instructions below:
1. use the measurements indicated in the drawing for the
foundations
2. Arrange for one or two pipes for the passage of electric cables
3. Assemble the 4 clamps on the anchoring plate and fix them
with the 4 bolts issued with the motor
4. Pour the concrete and position the anchoring plate
WARNING: check that the plate be on a perfectly
levelled surface and parallel to the gate
5. Wait for the complete setting of the concrete
6. Unscrew the bolts fixing the base to the clamps and put the
motor on the plate
7. Adjust the 4 grains F to make the motor be perfectly levelled
8. Control that the motor is perfectly parallel to the gate, then
insert the 4 washers R and lightly screw the 4 bolts D
9