5  LCS-Tool
igure 16: LCS-Tool - list of all inverters connected to the
Inverter Manager
13. If sufcient PV power is present and the grid
code conditions are met, the inverter starts the
operation. or battery storage systems, a
successful battery start and the fulfllment of the
Grid-Code requirements is necessary.
igure 17: LCS-Tool - commissioning report
28
IMVIOBOX-IA-xx-18
SMA Solar Technology AG
14. During commissioning it is possible to
download a commissioning report in the
Reports menu. The report contains information
about inverter settings, including actual
disconnection values for each inverter. By
clicking the folder icon in the menu Reports, it
is possible to open a folder for commissioning
reports (including grid code information).
Installation Manual