Descargar Imprimir esta página

Argo DRY PURY EVO 11 Instrucciones De Uso página 33

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 72
employed, and the appropriate percentage of gas (25 % maximum) is confirmed. Leak detection fluids are suitable
for use with most refrigerants but the use of detergents containing chiarine shall be avoided as the chiarine may
react with the refrigerant and corrode the copper pipe-work. If a leak is suspected, all naked flames shall be
removed/extinguished. If a leakage of refrigerant is found which requires brazing, all of the refrigerant shall be
recovered from the system, or isolated (by means of shut off valves) in a part of the system remote from the leak.
For appliances containing flammable refrigerants, oxygen free nitrogen (OFN) shall then be purged through the
system both before and during the brazing process.
Removal and evacuation
When breaking into the refrigerant circuit to make repairs or for any other purpose conventional procedures shall
be used. However, for flammable refrigerants it is important that best practice is followed since flammability is a
consideration.
The following procedure shall be adhered to:
remove refrigerant;
purge the circuit with inert gas; evacuate;
purge again with inert gas;
open the circuit by cutting or brazing.
The refrigerant charge shall be recovered into the correct recovery cylinders. For appliances containing flammable
refrigerants, the system shall be flushed with OFN to render the unit safe. This process may need to be repeated
several times. Compressed air or oxygen shall not be used for purging refrigerant systems. For appliances
containing flammable refrigerants, flushing shall be achieved by breaking the vacuum in the system with OFN
and continuing to fill until the working pressure is achieved, then venting to atmosphere, and finally pulling down
to a vacuum. This process shall be repeated until no refrigerant is within the system. When the final OFN charge
is used, the system shall be vented down to atmospheric pressure to enable work to take place. This operation
is absolutely vital if brazing operations on the pipe-work are to take place. Ensure that the outlet for the vacuum
pump is not close to any ignition sources and that ventilation is available.
Charging procedures
In addition to conventional charging procedures, the following requirements shall be followed.
Ensure that contamination of different refrigerants does not occur when using charging equipment. Hoses or
lines shall be as short as possible to minimise the amount of refrigerant contained in them.
Cylinders shall be kept upright.
Ensure that the refrigeration system is earthed prior to charging the system with refrigerant.
Label the system when charging is complete (if not already).
Extreme care shall be taken not to overfill the refrigeration system.
Prior to recharging the system, it shall be pressure-tested with the appropriate purging gas. The system shall be
leak-tested on completion of charging but prior to commissioning. A follow up leak test shall be carried out prior
to leaving the site.
Decommissioning
Before carrying out this procedure, it is essential that the technician is completely familiar with the equipment and
all its detail. lt is recommended good practice that all refrigerants are recovered safely. Prior to the task being
carried out, an oil and refrigerant sample shall be taken in case analysis is required prior to re-use of reclaimed
refrigerant. lt is essential that electrical power is available before the task is commenced.
1. Become familiar with the equipment and its operation.
2. Isolate system electrically.
3. Before attempting the procedure, ensure that:
mechanical handling equipment is available, if required, for handling refrigerant cylinders;
all personal protective equipment is available and being used correctly;
the recovery process is supervised at all times by a competent person;
recovery equipment and cylinders conform to the appropriate standards.
4. Pump down refrigerant system, if possible.
5. lf a vacuum is not possible, make a manifold so that refrigerant can be removed from various parts of the
system.
6. Make sure that cylinder is situated on the scales before recovery takes place.
7. Start the recovery machine and operate in accordance with manufacturer's instructions.
8. Do not overfill cylinders. (No more than 80% volume liquid charge).
9. Do not exceed the maximum working pressure of the cylinder, even temporarily.
10. When the cylinders have been filled correctly and the process compieted, make sure that the cylinders and
the equipment are removed from site promptly and all isolation valves on the equipment are closed off.
11. Recovered refrigerant shall not be charged into another refrigeration system unless it has been cleaned and
V 04/23
33

Publicidad

loading

Este manual también es adecuado para:

Dry pury evo 13