Commissioning, Operation - WIKA D-1-7 Serie Manual De Instrucciones

Transmisor de presión
Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

6. Commissioning, operation

6. Commissioning, operation
CAUTION!
GB
Prior to commissioning, the pressure transmitter must be subjected to a visual inspection.
Check the diaphragm for any visible damage, since this is a safety-relevant component.
Leaking fluid is indicative of damage.
Only use the pressure transmitter if it is in perfect condition with respect to safety.
6.1 Making the mechanical connection
Required tool: Open-ended spanner (spanner width 27 or 41), screwdriver
Remove the protection cap not until shortly before installation. During
installation, ensure that the diaphragm is not damaged (with model
D-11-7).
The sealing faces at the instrument have to be undamaged and clean.
Only ever screw in, or unscrew, the instrument via the spanner flats.
Never use the case as a working surface.
The correct torque depends on the dimensions of the pressure connec-
tion and the gasket used (form/material).
When screwing in, do not cross the threads.
For information on tapped holes and welding sockets, see Technical
Information IN 00.14 at www.wika.com.
12
WIKA operating instructions pressure transmitter model D-1x-7

Publicidad

Tabla de contenido
loading

Tabla de contenido