2. Installation
2.8 Connection of IEC cables to output receptacles
1
34008030EN/AD - Page 20
1 - Connect the equipments to the UPS
using the cables (49).
It is preferable to connect the priority
2
equipments to the four outlets (2) and the
non priority equipments to the four outlets
44
(1) that can be programmed in pairs (1 and
2).
Connect any high-power devices to the
16 A outlet (3).
To program shutdown of outlets (2) during
operation on battery power and thus
optimise the available backup time, the
EATON communication software is
required.
49
2 - Fit the connection securing system (44)
that prevents the plugs from being pulled
out accidentally.
3