4 Installing the inverter
4.4
Minimum clearances
75
B + 124
24
4.5
▶
75
4.6
1.
2.
3.
Condition: The load-bearing capacity of the wall is sufficient
B + 124
▶
▶
Requirements for the installation site
Ensure that the following requirements are satisfied:
–
The minimum clearances have been maintained
–
The direct current cable can be laid from the photo-
voltaic modules to the inverter
–
The alternating current cabling can be laid to the
meter cabinet
–
The installation site is fixed, vertical and level
–
The installation site is not exposed to direct sunlight
when installing on an external wall
–
The immediate installation environment is difficult to
ignite
–
The installation site is free from continuous vibrations
–
The installation site meets the requirements of cli-
mate class 4K4H in accordance with IEC 60721-3-4
–
An Internet router is available for using the web portal
–
The data connections for connecting other approved
products can be laid to the inverter
Wall-mounting the product
Check the load-bearing capacity of the wall.
Note the total weight of the product.
Only use fixing material that is permitted for the wall.
Use a spirit level to align the mounting plate horizontally
on the wall, as shown in the figure.
Use four screws to secure the mounting plate to the wall.