Regular maintenance of the entire photovoltaic installation
by a qualified competent person is a prerequisite for ensur-
ing that the system is constantly ready for operation, reliable
and has a long service life. The product manufacturer recom-
mends that you sign a maintenance contract.
When carrying out maintenance work, observe the gen-
eral safety information in the section on safety.
10.1

Complying with the maintenance plan

Carry out the maintenance work in accordance with the
maintenance schedule in the appendix.
10.2
Checking the components of the
photovoltaic installation
Check all of the components of the photovoltaic installa-
tion in accordance with your inspection and maintenance
instructions.
10.3

Checking the inverter

1.
Check the event log and, if required, carry out
troubleshooting (→ Page 33).
2.
Check the current annual yield and compare this with
the previous year's yield from the last test report.
3.
If you notice a significant deterioration in the annual
yield when compared to the previous year's yield, carry
out troubleshooting (→ Page 33).
10.4

Checking the installation site

Ensure that the requirements for the installation site
(→ Page 24)are complied with.
10.5

Checking the generator characteristic

Open Main menu → Gener. ch. curve.
1.
The inverter receives the photovoltaic generator
characteristic and then displays it.
2.
Ensure that the photovoltaic modules are not partially in
shadow.
If the curve is level at the top, the inverter may not
have been able to feed in any more power.
3.
Ensure that the photovoltaic installation corresponds to
the planning specifications and is configured correctly.
10.6
Preparing for maintenance work on the
electrical installation
1.
Temporarily decommission (→ Page 34)the photovoltaic
installation for maintenance work.
2.
Observe the requirements and safety warnings for the
electrical installation (→ Page 29).
34
10.7

Checking the electrical installation

10.7.1 Checking the protective earthing
If protective earthing is installed, check the cabling of the
protective earthing to ensure that it is working correctly.
10.7.2 Checking the insulation and stability of the
cabling
1.
Check the cabling, insulation and plug connections for
cleanliness, integrity and stability.
2.
If you notice a fault, document it and eliminate it imme-
diately.
10.8

Writing the maintenance report

1.
Document the maintenance work that was carried out in
a maintenance report.
2.
Pass the maintenance report on to the end user.
3.
Point out to the end user that they must always keep
the maintenance report safe.
10.9

Cleaning the inverter

1.
Check the inverter for dirt.
2.
Clean the surface with a slightly damp cloth and a little
solvent-free soap.
3.
Only use max. 2 bar compressed air to clean the cool-
ing fins behind the product casing.

10.10 Completing maintenance work

Start up (→ Page 31) the photovoltaic installation again
once the maintenance work is complete.

11 Decommissioning

11.1

Temporarily decommissioning

The photovoltaic installation can be temporarily decommis-
sioned.
Switch off the circuit breaker (fuse off).
Secure the circuit breaker against being switched on
again by mistake or without authorisation.
Switch the load isolator to position (0) to switch off the
power supply to the inverter.
Secure the load isolator against being switched on again
by mistake or without authorisation.
Installation and maintenance instructions VPV I 0020273427_02

Publicidad

Capítulos

Tabla de contenido
loading

Este manual también es adecuado para:

Vpv i 1500/2Vpv i 2000/2Vpv i 2500/2Vpv i 3000/2Vpv i 4000/2

Tabla de contenido