OPERATION
MACHINE SETUP
INSTALLING PAD
NOTE: Consult your authorized distributor for pad
recommendations.
Pad Specifications required:
S
For 2000 RPM burnishing.
S
25.4mm (1.0 in) thickness
S
508mm (20 in) dia. with 89mm (3.5 in) center hole.
NOTE: Machine is not designed for spray buffing.
1. Turn the main power switch off and tilt the
machine back on its rear wheels (Figure 4).
FOR SAFETY: Before leaving or servicing
machine, stop on level surface and turn off
machine.
NOTE: For safety, when machine is tilted on its rear
wheels, power to the pad motor automatically shuts off.
FIG. 4
ATTENTION: Do not leave machine tilted back for
an extended time, battery acid may leak.
2. Remove the plastic center lock from pad driver by
turning the lock counterclockwise.
3. Position the pad centered on the pad driver and
replace the centerlock securely (Figure 5).
FIG. 5
8
Home
Find... Go To..
NOTE: Make sure centerlock does not cross thread or
floor damage may occur.
ATTENTION: Do not operate machine without a
pad and/or centerlock in place.
4. After installing pad, return machine to operating
position.
INSTALLING DUST CONTROL BAG
1. Open the dust control bag compartment at the
front of the machine.
2. Slide the bag over the plastic snout. Close
compartment (Figure 6).
FIG. 6
3. Empty or replace the dust bag daily. Do not allow
bag to fill beyond half full.
ADJUSTING THE CONTROL GRIP HEIGHT
The machine has three control grip height settings.
1. Locate the two spring loaded levers below the
console (Figure 7).
2. Squeeze the levers together and lift or lower
control grips to a comfortable operating height
(Figure 7).
FIG. 7