If the supporting surface not already exists:
1.
Perform the foundation excavation to accommodate the foundation plate.
2.
Prepare the ducts for the passage of electrical cables.
3.
On the foundation plate, fix the four fangs by placing a nut and a washer on the upper and lower sides of the plate (Fig.5).
4.
Make the casting of concrete and, before starting the grip, place the foundation plate flush of the surface, parallel to the boom
and perfectly leveled (Fig.6).
5.
Wait until the concrete is completely taken; usually, at least two weeks.
6.
Remove the four upper nuts and washers from the fangs.
7.
Open the cabinet and place it correctly at the brackets and pipes for the passage of electric cables (Fig.8).
8.
Lock the cabinet with the appropriate nuts and washers just removed.
WARNING!
The fixing surface must be perfectly flat, smooth and of such dimensions that it can withstand the weight of the entire
structure to be installed.