7 Commissioning
7
Commissioning
7.1
Commissioning Procedure
This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Procedure
1.
Commission the product.
2.
Establish a connection to the user interface of the product.
There are various connection options to choose from for
this:
• Direct connection via WLAN
• Connection via WLAN in the local network
• Connection via Ethernet in the local network
3.
Change the network configuration, if necessary. The auto-
matic network configuration recommended by SMA Solar
Technology AG via DHCP server is activated by default.
4.
Carry out the configuration using the installation assistant.
Make the following settings:
• Administrator registration
• Device configuration (settings at the point of
interconnection, charging settings)
• Product settings
• Adding Devices (Energy Meter,
Sunny Home Manager 2.0)
• Grid management services
5.
To monitor the system in the Sunny Portal and view the
data visually, create a user account in the Sunny Portal
and create a system in the Sunny Portal or add devices to
an existing system.
7.2
Commissioning the Product
Requirements:
☐ The product must be correctly mounted.
40
EVCxx-10-BE-en-11
SMA Solar Technology AG
See
Section 7.2, page 40
Section 8.1, page 44
Section 7.3, page 43
Section 7.4, page 43
https://www.sunnypor-
tal.com
Operating manual