Descargar Imprimir esta página

Standard Application - ABB TTR200 Instrucciones Para La Puesta En Funcionamiento

Transmisor temperatura montaje en rail
Ocultar thumbs Ver también para TTR200:

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 51
Electrical connection
Pos: 11.11 /Überschriften/1.1/1-spaltig/S - U/Standardanwendung @ 16\mod_1198073912500_3101.doc @ 146614
4.3

Standard application

Pos: 11.12 /Elektrischer Anschluss/Temperatur/TTR200/Signal-/Versorgungsanschluss Teil 1 @ 16\mod_1198168131718_3101.doc @ 146748
Fig. 3
A Transmitter
When connecting transmitters and power supplies, observe the following specification:
U
Mmin
Where
U
Mmin
U
Smin
R
:
Ltg
For HART functionality, use power supplies or SPS input cards with HART mark. If this is not
possible, the interconnection must have a resistance ≥ 250 Ω (< 1100 Ω).
The signal line can be connected with or without ground. When connecting the ground (minus
side), make sure that only one side of the contact is connected to the equipotential bonding
system.
8 - EN
Field
≤ U
+ 0.02A x R
Smin
Ltg
: Minimum operating voltage of transmitter (refer to technical data for transmitter)
: Minimum supply voltage of repeater power supply / SPS input
Line resistance between transmitter and power supply
B Power supply / SPS input with supply