For The Plumber
Begin by planning the installation and obtaining the
needed supplies:
•
3/8" soft copper tubing
•
3/4" rigid drain tubing
•
3/4" FPT fitting for bin/reservoir drain connec-
tion
•
1/2" FPT fitting for condenser drain connection
•
3/8" FPT fitting for water cooled condenser inlet
connection
1. Connect cold potable water to the 3/8" male flare at
the back of the cabinet. A water filter and hand shut off
valve is recommended. Flush the water line prior to
connecting to the ice machine.
If water cooled, connect a separate water inlet line to the
water cooled condenser inlet fitting. It should also have a
hand shut off valve.
Water Cooled
Inlet
Water Cooled
Drain
Drain Receptacle
Plumbing Connections, Water Cooled Shown
A loop of copper tubing may be used between the ice
machine and the water supply. This will allow the ice
machine to be pulled out from its installed location
without disconnecting the water line.
2. Connect a drain tube to each drain connection (water
cooled drain must be separate).
3. Route the drain tubes to the building drain receptacle.
For The Electrician
Connect 50 Hz models to the correct voltage and fuses.
If the cord becomes damaged, the part number for a
replacement is 12-1638-18.
The electrical disconnect switch with fuse protection
must be a two pole type with a minimum of 3 mm
between open contacts.
Follow All Local Codes - This Unit Must Be Grounded.
Do not use extension cords and do not disable or by-pass
ground prong on electrical plug.
After Utility Connections:
1. Level the cabinet, use the leg levelers on the
end of the legs to adjust the cabinet
height. (Legs should have been
installed when the unit was
unpacked). Check for levelness at
5
the reservoir.
2. Wash out the bin and hood.
If desired, the interior of the
bin could be sanitized.
3. Locate the scoop, wash it
and have it available for use
when needed.
Reservoir and
Bin Drain
Field Supplied
Filter and Hand
Valve
Potable water inlet