3 Final assembly and installation of oneAdvanced 10–14 PE
3.3.2
Drilled holes for Carat S tank inlet and outlet
The holes for the inlets and outlets must be made with a Ø 124 core drill.
The drilling heights are given in the table below:
Size
Tank
Inlet H
Outlet H
3.3.3
Position of the outlet pipe
The outlet pipe's position and alignment depends on the position of the dividing baffle. The distance be-
tween the dividing baffle and the leading edge of the straight outlet pipe is 460 mm. The dividing baffle
point here is the outer surface of the topmost, centre rib! During installation, the emergency overflow is
pushed about 60 mm over the outlet pipe.
Preliminary clean-
ing/sludge storage
tank
H
10 PE
14 PE
4800 l
6500 l
190 mm
210 mm
195 mm
215 mm
460
SBR reactor
Dividing baffle
Outlet pipe
17 / 144
460