Installation and electrical connection
Install the supplied attachment point (provided by the customer) on the pressure port.
1
Pressure connection
4
2
Load bar
3
Fixation load bar/pressure connection
3
4
Attachment point for angular loading up to 90 °
Load bar with the corresponding bearing capacity for fixation of the attachment point
Attachment point for angular loading up to 90 ° (e.g. "Theipa" type)
Fixation material for the load bar
1. Place the load bar onto the pressure connection and attach it using two holes that are
opposite each other.
2. Fix the attachment point to the load bar.
▶ Attachment point installed, pump prepared for attaching.
Preparatory tasks
1
Bearing surface
3
2
Transport frame
3
Attachment point hydraulics
4
Attachment point motor
The transport frame lies horizontally on a firm bearing surface.
2x lifting equipment with sufficient bearing capacity are provided.
A sufficient number of approved items of lifting gear are provided.
1. Attach 1st lifting equipment to the hydraulics attachment point.
2. Attach 2nd lifting equipment to the motor attachment points.
▶ Pump ready for lifting and aligning.
Lift and align the pump
Preparatory tasks completed.
Weather conditions permit unloading.
1. Slowly lift the pump using both items of lifting equipment. CAUTION! Make sure that
the pump remains horizontal!
2. Remove transport frame.
3. Use the two items of lifting equipment to slowly move the pump into the vertical posi-
tion. CAUTION! Make sure that the housing parts do not touch the ground. The high
point loads damage the housing parts.
4. Once the pump is set upright, loosen the lifting gear at the hydraulics.
▶ The pump is aligned and ready to be set down.