Reduced charging current when down-
grade input is energised
6,7,8
Max. amperage - building connection
6.1.2 Setting the maximum charging current
The tasks described in this section may only
be carried out by a qualified electrician.
The maximum charging current of the charging
point can be set via DIP switches 1, 2 and 3 on bank
S2.
AMTRON® 4You 300 22
The maximum charging current can be set to 6 A,
10 A, 13 A, 16 A, 20 A, 25 A or 32 A.
DIP switch setting (bank S2)
1
2
OFF
OFF
ON
OFF
OFF
ON
ON
ON
OFF
OFF
ON
OFF
OFF
ON
The ON - ON - ON settings are invalid for configur-
ing the maximum charging current (the upper LED
of the LED status display lights up red). If these set-
tings are selected, a new master RFID card can be
programmed ("taught").
1 "6.5.2 Managing RFID cards" [} 34]
AMTRON® 4You 300 11
The maximum charging current can be set to 6 A,
10 A, 13 A or 16 A.
22
Max. char-
ging cur-
3
rent [A]
OFF
32
OFF
25
OFF
20
OFF
16
ON
13
ON
10
ON
6
DIP switch setting (bank S2)
1
2
OFF
OFF
ON
OFF
OFF
ON
ON
ON
OFF
OFF
ON
OFF
OFF
ON
The ON - ON - ON settings are invalid for configur-
ing the maximum charging current (the upper LED
of the LED status display lights up red). If these set-
tings are selected, a new master RFID card can be
programmed ("taught").
1 "6.5.2 Managing RFID cards" [} 34]
6.1.3 Setting up authorisation through RFID
The tasks described in this section may only
be carried out by a qualified electrician.
Authorisation occurs through an RFID card and a
local whitelist. Up to 10 RFID cards can be managed
in the whitelist. The RFID cards included in the de-
livery contents are already programmed and in-
cluded in the local whitelist.
u Set DIP switch 3 on bank 1 to "ON".
6.1.4 Set unbalanced load limitation
The tasks described in this section may only
be carried out by a qualified electrician.
Unbalanced load refers to the uneven loading of
the phases of a three-phase alternating current net-
work. In Germany, for example, the maximum differ-
ence between two phases at the mains connection
point is 20 A (in accordance with VDE-N-AR-4100).
u Observe applicable national regulations.
u Set DIP switch 2 on bank S1 to "ON".
Max. char-
ging cur-
3
rent [A]
OFF
16
OFF
16
OFF
16
OFF
16
ON
13
ON
10
ON
6