VERIFICHE DI PRIMA INSTALLAZIONE - SOLLEVATORE TIPO RAV ...
N° MATRICOLA ...
Verifica distanza delle pedane dai muri dove è installato (consigliato 1500 mm) ≥ 700 mm
Verifica distanza interna pedane ≥ 828 mm
Verifica altezza di sollevamento dal piano pavimento a piano pedane (soll. incassato): H ≥ 1675 mm
Verifica altezza di sollevamento dal piano pavimento a piano pedane (soll. a pavimento): H ≥ 1910 mm (RAV630.1),
H ≥ 1925 mm (RAV630.2)
Livellamento base mettendo eventualmente spessori
Serraggio tasselli fissaggio basi al pavimento
Serraggio tubi idraulici da centralina a basi
Controllo livello olio centralina
Controllo allacciamento rete e collegamento cavi
Attivazione sicurezze
Collegamento impianto pneumatico
Spurgo aria impianto idraulico
Verifica comandi elettrici (l'interruttore generale, pulsante salita, pulsante discesa)
Controllo funzionamento valvola di riallineo pedane e allineamento delle stesse
Controllo inserimento arpioni su cilindri
Controllo funzionamento pressostato
Controllo funzionamento cicalino
Controllo tempi di salita e discesa a pieno carico
DATA
FIRMA INSTALLATORE
INITIAL INSTALLATION INSPECTIONS - LIFT TYPE RAV ...
SERIAL NUMBER...
Check distance of platforms from any walls (recommended value 1500 mm) ≥ 700 mm
Check distance between platforms ≥ 828 mm
Check elevation height from floor to platform surface (recessed installation): H ≥ 1675 mm
Check elevation height from floor to platform surface (floor-mounted lift): H ≥ 1910 mm (RAV630.1),
H ≥ 1925 mm (RAV630.2)
Level base, place shims under bases if needed
Tighten plugs anchoring bases to floor
Tighten hydraulic pipes connecting hydraulic unit and bases
Check oil level in hydraulic unit
Check mains and cable connections
Operate safety devices
Pneumatic system connection
Bleed air from hydraulic system
Check power controls (main switch, up button, down button)
Check operation of platform realignment valve and platform alignment
Check that safety catches engage properly in cylinders
Check pressure switch operation
Check buzzer operation
Check up/down times with full load
DATE
INSTALLER SIGNATURE
88
0589-M001-0
FIRMA UTILIZZATORE
USER SIGNATURE
RAV630.1 - RAV630.1 I
RAV630.2 - RAV630.2 I

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

Rav630.1 iRav630.2Rav630.2 i

Tabla de contenido