Mounting Positions; Vertical Installation In Riser; Vertical Installation In A Drop Line; Horizontal Installation In Case Of Measurement Of Liquids - ABB CoriolisMaster FCB300 Serie Instrucciónes De Puesta En Marcha

Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 165
4.6

Mounting positions

The flowmeter operates in any mounting position. The ideal
installation position is vertical with flow from bottom to top.
4.6.1

Vertical installation in riser

Fig. 6:
Vertical installation, self-draining
4.6.2

Vertical installation in a drop line

Make sure that the flowmeter sensor is always completely full
while measurements are being taken.
A pipeline reduction or an orifice must also be installed
underneath the flowmeter sensor. The cross-section of the
pipeline reduction or orifice must be smaller than the cross-
section of the pipeline in order to prevent the flowmeter
sensor from running dry while measurements are being taken.
Fig. 7:
Vertical installation in a drop line
1 Supply reservoir | 2 Flowmeter sensor |
3
Orifice or pipe constriction
16 - EN CI/FCB300-X1 Rev. C | CoriolisMaster FCB330, FCB350
G10302
1
2
3
4
5
G00305
| 4 Valve | 5
Product reservoir
4.6.3
Horizontal installation in case of measurement of
liquids
Fig. 8:
Horizontal installation (liquids)
4.6.4
Horizontal installation in case of measurement of
gases
Abb. 9:
Horizontal installation (gases)
In case of measurement of gases ensure that the transmitter
housing or the terminal box pointing downwards.
G10303