There are no defaults on mobile parts and rail: corrosion, cracks...
GB
2
Check that all components are present (rails, fixings, bars, stops).
3
Any cantilever (until end stop) lower than 200 mm.
4
Maximum space between two brackets is less than 6 m.
5
A bracket is placed on both sides of a corner (immediately next to the corner).
Two brackets minimum before and after the corner, separated by 650 mm
maximum.
6
Rail brackets are placed on interfaces compliant with norm EN 795-D
2012 and TS 16415:2013 for strength (that is, load strength higher than
14000 N in the fall direction).
7
At least two brackets need to be installed on each rail.
8
A stop end is set at each rail end.
9
At least 1 sign plate by rail fully filled.

7.3. Maintenance

Rails must be immediately withdrawn from use:
• if security is uncertain, or
• if they have been used to stop a fall.
It should not be used anymore unless a competent
technician has authorized its reuse by writing, refer to
section 1 item 18.
Before any use of the rail:
• Visual check of the good conditions
• If a component is damaged, rail cannot be used
anymore. It must be condemned and the defective
components shall be replaced after a structure check.
This visual check consists of an analysis of the good
state of the components (rail, brackets, intermediary
parts, slider, brackets tightening, proper functioning,
marks readability).
travrail rail does not need any particular maintenance,
apart from a correct cleanliness. If dirty, clean the rail
with clear water and let it dry naturally. The rail must be
kept clean to ensure a smooth gliding of the slider. No
chemical product shall be used on the rail.

7.4. Annual inspection

It is obligatory to check carefully the rail travrail at least
once a year. The person in charge of the checking
must be competent, and must master this installation,
operating and maintenance manual, as well the work
at height regulation. The operator's safety is linked to
the efficient maintenance and to the resistance of the
equipment.
Table below represents the check points list and
its results must be entered on the inspection sheet
found in the centre of this manual. On that sheet, X =
the commissioning date.
12
CHECK POINTS
.
After each check, it is obligatory to fulfil the sign
plate by a sticker or a marking at the area provided for
this purpose.
CHECK POINTS
1
There are no defaults on mobile parts and rail:
corrosion, cracks...
2
Check that all components are present (rails, fixings,
bars, stops).
3
A stop end is set at each rail end.
4
Removable stop ends return to its closed position
after a manual opening.
5
Brackets are properly fixed, without any rattle, which
may be a sign of bolting loosening.
6
At least sign plate by rail legible and fully filled.
7
Sliders do not have any defaults and are not clogged.
If needed, disassemble and clean the slider (ask the
.
manufacturer)
A
Inspector's name.
B
Date of inspection.
C
Inspection OK = YES/NO.
D
Faults eliminated on date.
E
Validation issued on date.
F
Inspector's signature.

8. Use restrictions

PPE system has to be linked with rail via a connector
EN 362 set up on slider.
travrail rail is intended exclusively for hooking personal
protection device against height fall.
REMARKS