Measuring Pro Station – Operating instructions
12 Commissioning
12.1 General information on using MPS Stations
The stations of the MPS are generally delivered
•
Fully assembled
•
Individually adjusted and ready for use
•
Pre-commissioned
•
Tested
Commissioning is normally limited to visual inspection in order to ensure correct tubing connections, wiring
and operating voltage supply.
All components, tubing connections and cabling are clearly identified, so that all of the connections can be
readily restored.
12.2 Technical equipment of the workstation
You will require the following items in order to commission the MPS station with the sample programs:
•
The assembled and adjusted MPS Station
•
A control console
•
A PLC board with 16 digital inputs and outputs
•
A power supply 24 V DC, 4 A, ≤ 100 W output power, SELV/PELV limited power source (LPS)
•
Compressed air supply: 600 kPa (6 bar)
•
A PC with installed PLC programming software
•
4 I/O cables (SysLink)
38
When stations are combined, the mechanical setup, as well as sensor positions and
settings, may have to be changed.
© Festo Didactic 8136944