Step 4.
Position and mount Brackets (Ladder: LRB, FRB/Tower: AIB, SPB,LPB) for attaching the next
Rail section: The span between consecutive brackets on the Rigid Rail Safety System should not exceed
60 in. (1.5 m). Position and loosely mount as many brackets as are needed to attach the Rail section.
Step 5.
Secure the next Rail section (Ladder: SR/Tower: LR) in the Brackets: Position the Rail between
the clamp halves on the Bracket. Tighten the M16 fastener and Jam Nut on each clamp to the torque
values identified in the Bracket's respective Parts Table. Reposition the Brackets as needed for proper
Rail alignment and tighten remaining fasteners to the torques values identified in the Parts Table.
Step 6.
Splice consecutive Rail sections together with a Rail Clamp (RC): Parts Table RC illustrates
installation of the Rail Clamp. Install the Rail Clamp on adjoining Rail ends as follows:
A.
Disassemble the Rail Clamp halves.
B.
Position the pinned Rail Clamp half on the adjoining Rail ends with the pins inserted through the
holes on the Rail ends.
C.
Position the remaining Rail Clamp halve on the pins extruding through the Rail ends.
D.
�nstall M16 fasteners and Jam Nuts and tighten to the torque values identified in Parts Table RC.
Step 7.
Continue mounting and splicing consecutive Rail sections up to the bottom Rail section:
Repeat Steps 4 through 6 to mount and splice consecutive Rail sections.
Step 8.
Position and mount Brackets (Ladder: LRB, FRB/Tower: AIB, SPB,LPB) for attaching the
bottom Rail section: The span between consecutive brackets on the Rigid Rail Safety System should
not exceed 60 in. (1.5 m). Position and loosely mount as many brackets as are needed to attach the Rail
section.
Step 9.
Secure the bottom Rail section (Ladder: SR/Tower: LR) in the Brackets: Position the Rail
between the clamp halves on the Bracket. Tighten the M16 fastener and Jam Nut on each clamp to the
torque values identified in the Bracket's respective Parts Table. Reposition the Brackets as needed for
proper Rail alignment and tighten remaining fasteners to the torques values identified in the Parts Table.
Step 10. Splice together the adjoining ends of the bottom Rail section and the previous Rail section:
Repeat Step 6 to install a Rail Clamp (RC) on the adjoining Rail ends.
Step 11. Attach the Bottom Rail Gate (Ladder: SRG-B/Tower: LRG-B): Parts Table SRG and LRG illustrate
installation of the Rail Gates on the Rigid Rail Safety System. Position the Bottom Rail Gate clamp halves
over the bottom end of the Rail and tighten the M16 fastener and Jam Nut to the torque values identified
in in the respective Parts Table. When properly positioned, the arrow on the Rail Gate should be pointing
upward.
oPeRATIon: General procedures for using the Railok 90 Rigid Rail Safety System are as follows:
WARNING: Before each use, carefully inspect the Railok 90 Rigid Rail Safety System per instructions in the
Inspection Schedule (Table 1).
Step 1.
Install the Railok 90 Shuttle on the Railok 90 Rigid Rail Safety System: The Railok 90 Shuttle
can not be attached or removed at intermediate locations on the Rigid Rail Safety System. Rail Gates
on each end of the Rigid Rail Safety System allow attachment of the Railok 90 Shuttle, but prevent the
Shuttle from traveling off the ends of the Rail assembly (see Parts Tables SRG and LRG). The Shuttle is
designed to travel freely up the Rail, but can not travel down the Rail without lifting up on the Energy
Absorber and Pivot Arm. Parts Table SH illustrates installation of the Shuttle on the Rigid Rail:
A.
To Install the Shuttle from the bottom end of the Rail:
end of the Rail. The Bottom Rail Gate (SRG-B/LRG-B) will open automatically as the Shuttle is
pushed upward through the gate.
B.
To Install the Shuttle from the top end of the Rail:
Pivot Arm upward and then slide the Shuttle downward on the top end of the Rail. The Top Rail Gate
(SRG-T/LRG-T) will automatically open as the Shuttle is pushed downward through the gate.
NOTE: The Railok 90 Shuttle must be attached on the Rigid Rail with the arrows on the Shuttle
Labels pointing up. For additional details regarding installation and operation of the Shuttle, see the
"Railok 90 Rigid Rail Safety System Shuttle Instruction" (5903046).
Step 2.
Don a Full Body Harness: Don and adjust the Full Body Harness per the manufacturer's instructions.
Step 3.
Connect the Railok 90 Shuttle to the Full Body Harness: Connect the Carabiner on the Railok 90
Shuttle to the Front Chest D-Ring on the Full Body Harness (see Parts Table SH). Be sure the gate on
the Carabiner is fully closed and locked.
Slide the Shuttle upward on the bottom
Lift up on the Energy Absorber to pivot the